About the Project:

This water main replacement project will replace approximately 3,300 feet of old, undersized cast iron water main installed in the 1880s that is original to the water system. This project will take place on South Street from Highland Street to Elm Street.

The existing pipe has experienced multiple breaks in the past that have interrupted service and caused other issues. The existing pipe will be replaced with 8-inch ductile iron main. The project will include installation of several fire hydrants and renewal of customer service connections.

Maine Water Company is planning this project in cooperation with the City of Biddeford's sewer separation and the Maine DOT's paving project on South Street.

The City of Biddeford along with Maine Water's respective projects have been awarded to Pratt & Sons Inc. out of Mechanic Falls, ME.

 

progressmeter65png
Phase I Complete, Phase II beginning April 2019

 

Traffic Update:

Maine Water Company's Contractor will have appropriate signs, barricades, and lighting to provide safe construction zones.

                                                                                                           

Project News:

  • The first half of the project has completed installation and services are online.
  • Our Contractor has completed the second half of the 2018 project phase from Southview Drive to State Street.
  • Phase II of the project is slated to begin soon in April 2019.